Table Rock Road Pipeline Construction Project Wrapping Up
- December 11, 2024 | Category: Ongoing Projects
As part of our Table Rock Road Pipeline Construction Project, Medford Water has installed 18,000 feet of new 42″ water transmission pipeline under and along Table Rock Road, from Vilas Road to our Robert A. Duff Water Treatment Plant (north of Kirtland Road).
Contractor Pilot Rock Excavation has done a great job of working efficiently and quickly to minimize the disruption associated with this work. The final waterline tie-in will take place this week, followed by clean up. The project is anticipated to be primarily wrapped up by December 20th, with the exception of a final paving inlay that will be completed in February or March of 2025 (weather permitting).
We thank drivers, residents, and businesses for their patience throughout this important infrastructure project, which will provide a seismically resilient connection from our water treatment plant to our distribution system and provide additional transmission capacity to support our growing community.
To learn more about this project, visit medfordwater.org/tablerock, call us at 541-774-2430, or email us at water@medfordwater.org.