Table Rock Road Pipeline Project

Medford Water will install a new water pipeline along a section of Table Rock Road, to provide a seismically resilient connection from our water treatment plant to our distribution system and provide additional transmission capacity to support our growing community.

Overview

Medford Water will install a new water pipeline along a section of Table Rock Road, to provide a seismically resilient connection from our water treatment plant to our distribution system and provide additional transmission capacity to support our growing community.

Project Description and Benefits

  • Medford Water will install 18,000 feet of new 42″ water transmission pipeline under and along Table Rock Road, from our Robert A. Duff Water Treatment Plant north of Kirtland Road to Vilas Road.
  • This project will not only provide additional water transmission capacity to support our growing community, but it will also provide a seismically resilient connection from our water treatment plant to the rest of our distribution system.
  • Contractor Pilot Rock Excavation will begin construction in November 2023. We will provide more information as it becomes available.

Below is preliminary map of the area; view and download a full-size version.

Lester McFall
Special Projects Manager

Project Schedule

The construction contract was awarded to Pilot Rock Excavation at the regular meeting of the Board of Water Commissioners on July 19, 2023. The anticipated construction schedule is February 2024 through May 2025. This schedule is subject to change; we will provide more information as it becomes available.

Project Documents

None at this time.

Project News

The anticipated construction schedule is February 2024 through May 2025. This schedule is subject to change; we will provide more information as it becomes available. Traffic will be impacted on Table Rock Road as we carefully install this vital infrastructure; please drive cautiously and be aware of changes to traffic patterns.

Sign up at the bottom of the page to receive email updates; be sure to check your spam folders as these messages can sometimes get filtered.

DateUpdate
June 2024The project is approximately 30% complete; crews are finishing up work near Wilson Road, then will move to the north end of project to install the next 2400’ for the next several weeks, ending just south of Mosquito Lane. Work in intersections will continue to take place during a combination of day and nighttime to ease traffic issues.
May 2024While roadwork continues at both ends of the project, boring will soon begin near the Table Rock Road at Bateman Drive intersection, and near Rogue Transfer & Recycling. From 7 p.m. PST May 13th through the 25th, Southbound lanes will be closed between Kirtland Road and Antelope Road; detours will be in place. This work is subject to change, and will facilitate future phases of the project, keeping it on track and running as efficiently as possible.
April 2024Work will soon begin near the Robert A. Duff Water Treatment Plant (located north of Kirtland Road). During this time, paving will continue at the south end of the project, near Vilas Road. Work at intersections will primarily take place at night, to ease traffic issues. We aim to complete project activities as efficiently as possible to minimize disruption to residents and travelers, and appreciate your continued patience.
March 2024Construction activities within the Table Rock Rd. and Vilas Rd. intersection will begin the week of March 4th-8th, taking place at night to ease daytime traffic issues, and lasting approximately a couple of weeks. Following that, day work will continue from Vilas Rd. towards Kirtland Rd. and our water treatment plant. Please drive cautiously and be aware of changes to traffic patterns, the active construction zone has a 35 mph posted speed limit.
February 2024Near the end of February, the contractor will begin excavation in various locations on Table Rock Road between 
our Robert A. Duff Water Treatment Plant north of Kirtland Road, to Vilas Road, to visually confirm 
the presence of utility lines. Nighttime work at the Vilas intersection was delayed slightly, but will begin in early March. Following that, day work will continue from Vilas towards Kirtland and our water treatment plant. The active construction zone will have a 35 mph posted speed limit; please drive with caution.
January 2024Contractor Pilot Rock Excavation will begin construction in the roadway in February 2024, beginning at our water treatment plant. Near the end of February, construction work will also begin at the Vilas Road intersection; work in the intersection will take place at night to ease daytime traffic issues. We will minimize impacts as much as possible, but these activities will result in temporary lane closures and traffic delays as we carefully install this vital infrastructure. Please drive cautiously and be aware of changes to traffic patterns.
September 2023Medford Water continues to receive materials for this project, and we are currently working with our partners at Jackson County and the City of Medford on required permitting and traffic control plans. Construction is anticipated to begin November 2023, beginning at the Vilas Road and Table Rock Road intersection, and continue to May 2025. Traffic patterns will be impacted for extended periods of time, so please consider alternate routes and drive carefully in construction zones.
July 2023Design and permitting of this project is complete, and the construction contract
was awarded by the Board of Water Commissioners to Pilot Rock Excavation on July 19, 2023. Medford Water pre-purchased the materials for this project in order to reduce costs and to better manage the long-lead times for pipeline components; the materials are currently being delivered to our storage location.